What is Overview of Hydraulic System of MSS660 Movable Scaffolding System?

FAQ 十一 15, 2012 What is Overview of Hydraulic System of MSS660 Movable Scaffolding System?已关闭评论
  1. ? Overview

1.1?? Hydraulic system of 660t movable scaffolding system is special hydraulic equipment designed and fabricated for ZZHZ, the system uses hydraulic elements, auxiliary parts with high quality in domestic market, featuring compact structure, reliable quality, reasonable design, convenient maintenance and other advantages, be in accordance with technical demands in GB3766-87 General-purpose Technical Conditions for Hydraulic System.

Movable scaffolding system

Movable scaffolding system

Read more »

What are Quality Warranty Measures for MSS660 Movable Scaffolding System?

FAQ 十一 14, 2012 What are Quality Warranty Measures for MSS660 Movable Scaffolding System?已关闭评论

Quality warranty check for MSS660 movable scaffolding system ensures the normal working of equipment after leaving factory, thus provide a guarantee for buyer”s convenience and save maintenance cost for sellers in the future, save unnecessary troubles for both buyers and sellers.

Read more »

What is Main Structure of Single Girder Bridge Crane?

FAQ 十一 12, 2012 What is Main Structure of Single Girder Bridge Crane?已关闭评论

Purpose and structure

LD electric single girder bridge crane (the following says crane) is a kind of light lifting equipment, used with CD1?MD1 and other electric hoists, lifting capacity 1-20t, span 7.5-22.5m, working environment -25?~+40?, humidity ?84?. It works under the environment without fire, explosion and corrosive matters and it is prohibited to lift liquid metal, and toxic, flammable and explosive objects. Work duty: intermediate work system?JC25%?

LD single girder bridge crane

LD single girder bridge crane

Read more »

What is Construction Period Analysis for MSS660 Movable Scaffolding System?

FAQ 十一 09, 2012 What is Construction Period Analysis for MSS660 Movable Scaffolding System?已关闭评论

Before we begin to use movable scaffolding system, we should keep in mind the construction period to construct one span girder, so that the construction? process can be ensured.

HZQ50-160t

HZQ50-160t

Construction period analysis for MSS660 movable scaffolding system is as followings:

1. Install reinforcing steel bar of bottom and web plate, lay pre-stressing hole and put in pre-stressed tendon. (1.5 days)

2. Install scattered internal formwork ?????(1 day)

3. Install reinforcing steel bar of top plate?? (1day)

4. Pour and maintain concrete (internal formwork loosing is included to reduce friction loss for pre-stressing tension)? ?????????????????(4 days)

5. Stretch-draw pre-stressed tendon. ???????(0.5 days)

6. Drop formwork to remove the connection between bottom formwork truss girder and bottom formwork connection bolts at the part of bridge axis (bottom formwork centre joint). Move laterally to separate the formwork, move longitudinally to cross piers, move laterally to close the formwork, lay bottom die and end die at pier top. (1.5 days)

10 days in total. Usually it is more appropriate to construct one span for 10 days in the normal construction, first span installation and commissioning could be finished in 1 month, the first two spans concrete girders can be arranged to produce according to the schedule 15 days per span because workers are not familiar with the condition.

How to Install and Check Structure of MSS660 Movable Scaffolding System?

FAQ 十一 08, 2012 1 Comment

Installation steps:

1. Install support frame, main girder, guide beam

MSS660 movable scaffolding system

MSS660 movable scaffolding system

1.1 Set up installation support. Level field between 14# abutment and J1 pier according to Installation Steps Drawing, and set up installation support and temporary pier for steel box girders and guide beam connection parts. Support height should meet the demand that steel box girder bottom part should be 5cm higher than support roller top surface. Built by steel pipes in the worksite, the support should meet the needs of bearing capacity in the installation process and ensure enough bearing capacity settling volume ?1cm.

Read more »

What are Construction Steps and Precautions for Movable Scaffolding System?

FAQ 十一 07, 2012 What are Construction Steps and Precautions for Movable Scaffolding System?已关闭评论
Movable scaffolding system

Movable scaffolding system

Construction steps and precautions

1. Construction steps

1.1 Movable scaffolding system main girder falls down, be divided, moves laterally

1.1.1 Remove suspender of rear anchoring device

1.1.2 Remove home-made bulk formwork at the top of pier;

1.1.3 Meanwhile steel box girder support jacks fall. The formwork separates from poured concrete girder, steel box girder is supported on support roller of longitudinal moving gearbox; remove formwork at centerline of MSS and connection bolts of cross girder. Check whether connection between formwork lateral moving device and left, right parts of formwork is been removed totally, little lateral moving divides MSS into two parts.

Read more »

What are Functions of Main Structure of Movable Scaffolding System?

FAQ 十一 06, 2012 1 Comment

?Structures and main functions

Upstroke movable scaffolding system

Upstroke movable scaffolding system

General dimension in working condition length 70m, width 19m, height 12m, from upper to bottom part, ZZHZ movable scaffolding system is made up of support frame, support gearbox, front and rear guide beam, main girder and lateral connection part, bottom die, side die and rear anchoring beam, anti-typhoon device, hydraulic system and walkway (stairs, platform) and other parts. Realize functions of automatic jacking of hydraulic system, lateral moving and longitudinal moving to cross piers. The complete machine can meet two-way construction demands: moving forward and moving backward construction.

Read more »

What is main structure of MSS660 Movable Scaffolding System Bridge Making Machine?

FAQ 十一 05, 2012 What is main structure of MSS660 Movable Scaffolding System Bridge Making Machine?已关闭评论

(1) Main structure

General dimension in working condition length 70m, width 19m, height 12m, from upper to bottom part, ZZHZ movable scaffolding system is made up of support frame, support gearbox, front and rear guide beam, main girder and lateral connection part, bottom die, side die and rear anchoring beam, anti-typhoon device, hydraulic system and walkway (stairs, platform) and other parts. Realize functions of automatic jacking of hydraulic system, lateral moving and longitudinal moving to cross piers. The movable scaffolding system bridge making machine? can meet two-way construction demands: moving forward and moving backward construction.

MSS movable scaffolding system

MSS movable scaffolding system

Read more »

How to operate electro-mechanical-hydraulic system safely of launching girder?

FAQ 十一 03, 2012 How to operate electro-mechanical-hydraulic system safely of launching girder?已关闭评论

With rapid development of China infrastructure, more and more construction machinery is demanded, and thus there is higher and higher technical requirements about construction machinery. Safe operations for electro-mechanical-hydraulic integration system from ZZHZ are as the following:

HZQ32-165t  Launching girder

HZQ32-165t Launching girder

Read more »

What is the Brief Introduction of MSS660 Movable Support System Bridge Making Machine?

FAQ 十 30, 2012 1 Comment

ZZHZ MSS30/660 movable support system bridge making machine is bridge construction equipment using methods of cast-in-situ and span by span construction, designed to meet 30m continuous box girder construction for Jin Tang Bridge. It features high stiffness of main girder, convenient installation of support frame, wide adaptation to pier body with different width and thickness.

MZ900S movable support system bridge making machine

MZ900S movable support system bridge making machine

Read more »