HZP1600 segmental assembly bridge erection equipment is made up of main frame, support structures, overhead travelling crane for lifting girders and transverse luffing mechanism.
Below main configuration is for your reference:
no |
parts |
quantity |
remark |
1 |
front support leg | 1 | |
2 |
rear support leg | 1 | |
3 |
auxiliary front support leg | 1 | |
4 |
auxiliary rear support leg | 1 | |
5 |
guide beam | 2 | |
6 |
main girder | 2 | |
7 |
gantry crane for lifting girders | 1 | |
8 |
suspender | 1 | |
9 |
10t overhead travelling crane | 1 | |
10 |
electrical system | 1 |